The West Wooster Water & Sewer Improvement project is scheduled to begin on Monday, September 19th. This project will involve the replacement of water and sewer mains along West Wooster Street from Church to Haskins and along Haskins from W. Wooster to Wallace. In addition to water and sewer mains, this project will replace the water and sewer service lines to the right-of-way line (approximately located on the homeowner side of the sidewalk). After the water and sewer improvements have been completed, the curbs and roadway will be replaced along W. Wooster and Haskins throughout the project area.
This project will involve digging in and around various trees. The impacted area has been assessed to determine which trees can be saved. Trees, selected for removal, will be removed in late September. Replacement trees will be planted during the fall 2023 or spring 2024 planting season.
This schedule is dependent upon weather and progress of work. The contract completion date for this project is June 1, 2023.